Updates on the Athletic Complex
Updates as of September 12, 2018
- Turf is being delivered on 9/12 and installation will begin on 9/18 and be complete by 10/1
- Paving will start 9/12 and should be done by 9/17 for the track and the semi circles at the ends of the fields (the parts that will eventually have rubber surface)
- Foundations for the new bleachers : 9/13
- Bleacher construction will be from 9/21 – 10/1
- Foundations for the light poles: 9/17 – 9/22
- Light poles/lights will arrive on 9/20 and will be installed by 9/30
- Scoreboard will be delivered on 9/17 and installed by 10/1
- Complete the rest of paving starting 10/1 and will be done by 10/5
- Fencing will start the first week of Oct and will take 2 weeks
- Rubberized track finish is scheduled to start 10/8 and will be done by 10/15
A couple of these items are weather dependent, but this is what is expected over the next three to four weeks.