Updates as of September 12, 2018

  • Turf is being delivered on 9/12 and installation will begin on 9/18 and be complete by 10/1
  • Paving will start 9/12 and should be done by 9/17 for the track and the semi circles at the ends of the fields (the parts that will eventually have rubber surface)
  • Foundations for the new bleachers :  9/13
  • Bleacher construction will be from 9/21 – 10/1
  • Foundations for the light poles: 9/17 – 9/22
  • Light poles/lights will arrive on 9/20 and will be installed by 9/30
  • Scoreboard will be delivered on 9/17 and installed by 10/1
  • Complete the rest of paving starting 10/1 and will be done by 10/5
  • Fencing will start the first week of Oct and will take 2 weeks
  • Rubberized track finish is scheduled to start 10/8 and will be done by 10/15