Updates on the Athletic Complex

Updates as of September 12, 2018

  • Turf is being delivered on 9/12 and installation will begin on 9/18 and be complete by 10/1
  • Paving will start 9/12 and should be done by 9/17 for the track and the semi circles at the ends of the fields (the parts that will eventually have rubber surface)
  • Foundations for the new bleachers :  9/13
  • Bleacher construction will be from 9/21 – 10/1
  • Foundations for the light poles: 9/17 – 9/22
  • Light poles/lights will arrive on 9/20 and will be installed by 9/30
  • Scoreboard will be delivered on 9/17 and installed by 10/1
  • Complete the rest of paving starting 10/1 and will be done by 10/5
  • Fencing will start the first week of Oct and will take 2 weeks
  • Rubberized track finish is scheduled to start 10/8 and will be done by 10/15
A couple of these items are weather dependent, but this is what is expected over the next three to four weeks.

Coming Events at RSU 18 District

Upcoming Events

  1. School Photos

    October 28
  2. MHS Flu Shot Clinic

    October 29
  3. China @ Windsor GV

    October 29 @ 3:45 pm - 4:15 pm
  4. Windsor @ China BV

    October 29 @ 3:45 pm - 4:15 pm
  5. Quarter 1 Ends

    October 30